Kalorama, DC - Whole House Renovation & Historical Restoration
NARI CotY "Grand" Award Winner 2006
Brief Explanation of the Scope of Work
When we first visited this vintage three story
townhouse, built in 1900, it was clear that it
would require a complete renovation. As both
the owner and the design/build remodeler for
this whole house remodel, our main focus was
on maximizing value, while restoring several
key historically-significant elements of the
house, as these were also of value for resale.
Unusual Constraints
or Challenges & Creative
Solutions
The house had 2400
square feet of space on the first, second and
third floors. By digging out,
waterproofing and finishing the basement, we
made it into a 3000 square foot house. We restored
and improved the exterior envelope of the house.
This included historically accurate windows,
a new roof, re-pointing, cleaning and repairing
the front masonry façade, rebuilding four
walls that comprised the rear elevations of the
house, adding a rooftop deck and re-doing the
front and rear yards .
We opened up and completely remodeled the kitchen
area so that it was integrated with the dining
and living areas at the front of the house. We
also added a half bathroom adjacent the kitchen,
remodeled three bathrooms and added one additional
bathroom in the basement.
We added high efficiency two zone heating and
cooling systems. While the house originally had
a boiler and radiators, we could not keep the
system as it was completely depreciated and reduced
the floor space in several key areas. We sistered
all of the joists on the first, second, and third
floors which allowed us to remove a central bearing
wall.
On the interior we restored two marble fireplaces
, strengthened, leveled and restored the staircase;
salvaged, reinstalled and refinished heart- of-pine
floors; and restored and added antique hardware
to the front door. Although we replaced all of
the interior doors and trim, we selected materials
that were consistent with those we removed. We
redesigned the living space on the second floor
to create an elegant master bedroom/bathroom suite.
We integrated a laundry center on the second floor
and a rear bedroom with its own bathroom. On the
third level, we restored the existing floor plan,
but added three closets. Parts of the front were
also power washed to remove soot and stains.
As one can see from the first floor design plan,
we removed almost all of the existing first floor
partition walls and opened up the interior space
to have an almost loft-like feel. High quality
Crystal kitchen cabinets and stainless steel
appliances were installed along with level 5
Blue Eyes granite counters to make the kitchen
an architectural focal point. The new owners
of the house really enjoy entertaining on this
level.
There were two
existing old marble fireplace mantles/surrounds
in the house. While some remodelers
might have chosen to replace the mantles, we
took special effort to restore them. This required
hiring a specialist to have them polished and
detailed in place. One of the fireplaces’ mantles
was so stained that we decided to obtain a salvaged
one, refinish it, and install it. It matched
almost perfectly. We invested over $2,000 to
restore both of these fireplaces.
Restoring the original
staircase from the first to third levels was
particularly challenging.
The staircases were at least an inch out of level.
We sistered the stringers with new LVL’s
and jacked up and also sistered the headers in
order to level and strengthen the stairwell.
We turned a number of new oak pickets to match
existing ones and opened up the stairwell on
the main level to increase the space visually.
The existing flooring on all three levels of
the house was fastened directly to the joists.
In order to strengthen the flooring, we pieced
in plywood sub-flooring between the joists from
underneath. This strengthened the floors and
added to the
life span of the antique heart pine.
In order to improve the energy efficiency of
this house, we invested in having Icynene insulation
sprayed onto the underside of the entire roof,
all exterior stud bays and all exterior basement
walls. This, in combination with fiberglass
insulation between floors and on interior walls
for soundproofing, made the project particularly
tight. We also had to underpin the two party
walls in order to lower the basement. This
required careful planning and execution in
order to complete the work safely and effectively.
In order to restore some of the front, we had
to make a number of new bricks to match the
existing white ones. At first we thought the
bricks were limestone. When we discovered that
they were solid cinderblock dipped in white
concrete, we experimented and figured out how
to make new matching ones on site.
One of our biggest challenges was access during
the project. Parking was very difficult and the
rear of the house did not have alley access.
Everything that came in and out of the house
had to be done by hand including dirt, concrete,
and demolition materials. The only thing we had
boomed into the house was the drywall package.
Working with the
neighbors was also time-consuming as the house
was almost a complete gut and underpinning the
party walls required their written consent.
At the rear of the house, there was an existing
two story structure that ended up having to be
taken down completely because it had inadequate
footings and was subject to the elements after
we had demolished much of it. Due to safety considerations
and quality concerns, we decided to take down
a good deal of brickwork we had hoped to save.
Overall Results
As an indication of how we added value to this
property, we sold it in less than two weeks for
about five percent over the asking price.
| 3rd Floor - Hallway
- View Of Access To Rear Deck |
| Basement - View
To Front Entrance |
| Before - 1st Floor
- Main Entrance |
| Before - 2nd Floor
Master Bedroom |
|